How to Review Work Requests
Review incoming work requests, approve or reject them, and convert approved requests into actionable work orders.
Quick Summary
Go to Requests, click on a pending request, review the details, then click Accept to approve or Reject to decline.
Before You Begin
- You must have Approver or Admin role
- Pending requests must exist to review
Step-by-Step: Review a Request
Step 1: View Pending Requests
- From the left sidebar, click Requests
- Filter by Status: Pending to see requests awaiting review
- Click on a request to open details
Step 2: Examine the Request
Review the submitted information:
| Section | What to Check |
|---|---|
| Subject | Is it clear what's being requested? |
| Priority | Is the priority level appropriate? |
| Description | Are there enough details? |
| Location | Is the location correct? |
| Images | Do photos show the issue clearly? |
| Requester | Who submitted this request? |
| Created Date | When was it submitted? |
Step 3: Make a Decision
Choose one of the following actions:
| Action | When to Use | What Happens |
|---|---|---|
| Accept | Request is valid and work should proceed | Status changes, can create work order |
| Reject | Request is invalid, duplicate, or unnecessary | Status changes to Rejected |
| Cancel | Request should be withdrawn | Status changes to Cancelled |
Step 4: Process the Decision
To Approve:
- Click Accept
- Request status changes to Accept
- Proceed to create a work order
To Reject:
- Click Reject
- Enter a reason (optional but recommended)
- Confirm rejection
- Requester is notified with the reason
Converting to Work Order
After accepting a request:
Step 1: Create Work Order
- From the accepted request, click Create Work Order
- The work order form opens with pre-filled data:
- Title from request subject
- Description from request
- Location from request
- Priority from request
Step 2: Complete Work Order Details
Add additional information:
| Field | What to Add |
|---|---|
| Assign To | Select technician or team |
| Due Date | When work should complete |
| Category | Type of work (if applicable) |
| Additional Notes | Instructions for technician |
Step 3: Save Work Order
- Review all fields
- Click Create
- Work order is created and linked to the original request
Real-World Examples
Example 1: Approve and Assign Urgent AC Repair
Situation: A high-priority request for a broken AC in a conference room needs immediate attention.
Solution:
- Open the request in Requests
- Verify the details:
- Location is correct
- Photos confirm the issue
- Priority is appropriate (High)
- Click Accept
- Click Create Work Order
- Add:
- Assign To: HVAC Team
- Due Date: Today (urgent)
- Notes: "Client meeting tomorrow - prioritize"
- Click Create
Result: HVAC team receives immediate notification and the work order appears in their queue with high priority.
Example 2: Reject a Duplicate Request
Situation: Someone submitted a request for a light outage that's already being addressed by another work order.
Solution:
- Open the duplicate request
- Verify it's truly a duplicate:
- Same location
- Same issue
- Existing work order in progress
- Click Reject
- Enter reason: "Duplicate request. This issue is already being addressed in Work Order #WO-2024-0542. Expected completion by Friday."
- Confirm rejection
Result: Requester is notified with the explanation and reference to the existing work order.
Example 3: Request Needs More Information
Situation: A vague request says "Something wrong with the elevator" but doesn't specify which elevator or what's wrong.
Solution:
- Open the request
- Note the missing details
- Add a comment asking for clarification:
- "Which elevator is affected?"
- "What specific issue are you experiencing?"
- "When did this start?"
- Wait for requester to respond
- Once clarified, proceed with approval or rejection
Result: Better information leads to more effective work order creation.
Example 4: Lower Priority and Approve
Situation: A request marked as "High" priority is for a minor cosmetic issue (small scratch on wall).
Solution:
- Open the request
- Assess the actual urgency
- Click Accept
- When creating work order:
- Change Priority to Low
- Set Due Date to next week
- Add note: "Cosmetic repair - schedule during regular rounds"
- Create the work order
Result: Work is scheduled appropriately without unnecessarily escalating resources.
Batch Processing
For multiple requests:
Filter and Sort
- Use filters to find related requests:
- Location: Group by building
- Priority: Address high priority first
- Date: Process oldest first
Bulk Actions
- Select multiple requests using checkboxes
- Available bulk actions:
- Accept Selected
- Reject Selected
Bulk rejection should include a clear reason that applies to all selected requests.
Request Review Best Practices
Response Time Goals
| Priority | Review Within |
|---|---|
| High | 2 hours |
| Medium | 24 hours |
| Low | 48 hours |
| None | 72 hours |
Quality Checks
Before approving, verify:
- Location is correct and accessible
- Issue description is clear
- Priority matches actual urgency
- Photos support the request
- Not a duplicate of existing work
When to Reject
Reject requests that are:
- Duplicates of existing work orders
- Outside your organization's responsibility
- Not actionable (too vague)
- Incorrectly submitted (wrong location)
Always provide a clear rejection reason to help the requester.
Troubleshooting
Can't Accept Request
| Issue | Cause | Solution |
|---|---|---|
| Button disabled | Insufficient permissions | Contact admin for Approver role |
| Error on accept | Technical issue | Refresh and try again |
Work Order Not Created
| Issue | Cause | Solution |
|---|---|---|
| No create option | Request not accepted first | Accept the request first |
| Form won't submit | Missing required fields | Fill all required work order fields |
Can't See All Requests
| Issue | Cause | Solution |
|---|---|---|
| List seems empty | Filter active | Clear all filters |
| Missing requests | Pagination | Check other pages or increase page size |
Related Articles
Need help? Contact Infodeck Support